Since the resumption of work after the Spring Festival, the project department of Zhongtai Jinhui Technology Co., Ltd. of China Chemical Engineering 13th Construction Co., Ltd. has responded positively to the requirements of the company and successfully completed the first node target after the resumption of work on February 20, 2023 with the concerted efforts of all project personnel.

Within a week after the resumption of work, there were always 105 workers on site, and 13 25-ton cranes and 10 dump cranes were concentrated in the project. The successful completion of this node target laid a solid foundation for the subsequent construction of the project.