On May 27, 2024, the Ministry of Industry and Information Technology revised the "Standardized Conditions for the Viscose Fiber Industry (2017 Edition)" and the "Interim Measures for the Administration of the Announcement of Standardized Conditions for the Viscose Fiber Industry", forming the "Standardized Conditions for the Viscose Fiber Industry (2024 Edition)" and the "Administrative Measures for the Announcement of Standardized Conditions for Viscose Fiber Enterprises". The new version is similar to the old one in terms of content framework, mainly adding content related to carbon emissions, and other details have been modified, supplemented or deleted.
2017 edition | New, deleted or adjusted content in the 2024 edition | |
Introduction | Emphasis on preventing low-level duplication and reducing resource waste | Emphasis on promoting green transformation and reasonably guiding the direction of industry development |
Enterprise layout | Emphasis on new construction in non-specific areas | Emphasis on concentrated construction of new projects in industrial parks |
The construction of new VFY projects are prohibited. Strictly control the construction of new VSF projects. New projects must have the conditions of replacing traditional raw materials such as cotton linter pulp and wood pulp through independent development, and realizing pulp and fiber integration, or having raw material bases that match the new capacity. | Delete this item | |
Advantageous enterprises mergers and reorganizations to enhance industrial concentration and overall competitiveness | Delete this item | |
Allow viscose fiber enterprises and scientific research institutions to build a production line for small or medium-scale trials with no more than 5kt/yr capacity and a differentiation rate of more than 90%. | Change the content of the test line to "hundred-ton small test line, thousand-ton pilot line and differential fiber line of no more than 30kt/yr capacity (differentiation rate> 90%)" - and move this content to the process equipment column. | |
Process equipment | Add the content of "new viscose fiber projects should have a stable source of pulp, and encourage enterprises to develop and apply new pulp (bamboo pulp, hemp pulp, mushroom grass pulp, recycled pulp, etc.)" | |
Delete the content of "the product differentiation rate of the total capacity of the expansion and reconstruction of viscose fiber projects is higher than 30%" | ||
Adopt efficient continuous impregnation, pressing and crushing combined machine to ensure the qualified composition and crushing degree of alkali cellulose; adopt advanced aging machine to ensure the stability of temperature and time of alkali cellulose aging; adopt automatic batching and feeding system, and the yellowing process is automatically controlled by program. The yellowing machine should have safety devices such as pressure relief facilities (pressure relief valve or pressure relief membrane); adopt high pressure difference viscose dissolution process and crushing and grinding equipment to improve the dissolution and filtration performance of viscose; adopt continuous automatic filtering device and waste viscose processing device, and add advanced plate and frame filtering device when necessary to ensure the spinnability of viscose; VSF spinning equipment is selected according to the requirements of different varieties. In principle, equipment with good airtightness and variable frequency speed regulation is used; the acid bath circulation system of the acid station should adopt acid bath degassing device and waste acid liquid recovery and treatment device; the recovery system should adopt multi-stage flash evaporation and sodium sulfate preparation device, and the amount of sodium sulfate prepared should be more than 60% greater than the amount produced; for strict process control of production, the DCS distributed automatic control system should be adopted throughout the line; it is required to make comprehensive and efficient use of resources such as condensed water, cooling water, waste water, and waste heat. | In the VSF spinning section, spinning machines, drawing machines and cutting machines must have good sealing properties to effectively reduce the unorganized emission of sulfur-containing waste gas; the VSF line recovery system must be equipped with sodium sulfate recovery equipment such as multi-stage flash evaporation or one-step nitrate extraction, and the sodium sulfate recovery rate must reach more than 60% of the production volume or more than 500 kg of sodium sulfate per ton of product; new construction, renovation and expansion of VFY and VSF projects should be well equipped with waste gas collection, supporting combustion, catalytic oxidation, biological treatment, biological adsorption and other devices to effectively treat volatile organic compounds, low-concentration sulfur-containing waste gas and other atmospheric pollutants; the wastewater treatment unit of the viscose fiber factory should be designed with reasonable closed collection measures and treatment facilities to collect and treat sulfur-containing waste gas; to promote technological progress and product development in the industry, viscose fiber enterprises and scientific research institutions are encouraged to use 100-ton small test lines, 1,000-ton pilot lines and differential lines of no more than 30kt/yr capacity (differentiation rate > 90%) for technical research and product development, etc. | |
Resource consumption | The water intake per ton of VFY≤235 tons; the water intake per ton of VSF≤55 tons; the reuse rate of production water≥90% | The water intake per ton of VFY≤230 tons; the water intake per ton of VSF≤50 tons; the reuse rate of production water≥92% |
The comprehensive energy consumption per ton of VFY≤4,000kg of standard coal. The comprehensive energy consumption per ton of VSF≤1,000kg of standard coal | The comprehensive energy consumption per ton of VFY≤3,200kg of standard coal. Comprehensive energy consumption per ton of VSF≤900kg of standard coal | |
Environmental protection | Hazardous waste must be handled by qualified units. | Hazardous waste and other solid wastes are effectively utilized and properly disposed of, and the standardized environmental management assessment of hazardous wastes should be up to standard. |
Newly built and expanded viscose fiber coal-consuming projects in key areas of Beijing-Tianjin-Hebei, Yangtze River Delta and Pearl River Delta should implement equal or reduced coal substitution. | Delete this item | |
Newly built and expanded VSF units should adopt advanced and reliable CS2 recovery units, and the total sulfur recovery should be more than 87%. | Delete this item | |
Carbon emissions | Viscose fiber enterprises are encouraged to carry out basic research and capacity building related to green factory construction, factory carbon verification, product carbon footprint, carbon labeling and product life cycle evaluation; viscose fiber enterprises are encouraged to formulate carbon reduction plans, carbon peak and carbon neutrality goals and disclose work progress regularly; viscose fiber enterprises are encouraged to equip solar street lights, photovoltaic panels and other carbon reduction projects according to the factory conditions, build and apply industrial green microgrids; viscose fiber enterprises are encouraged to adopt engineering facilities such as centralized heating, coal to gas, and coal to electricity to reduce corporate carbon emissions. | |
Quality management | Add the content of "intelligent manufacturing, digital workshop and smart factory construction. Improve the level of digital networking and intelligence, strengthen enterprise management, reduce production costs, and ensure product quality". | |
Safe production | Add the content of "the enterprise has not had a major or above production safety accident within one year". | |
Supervision and management | New (renovation and expansion) viscose fiber projects should comply with national laws and regulations and the requirements of this specification. The investment management, land supply, energy-saving assessment review, and environmental impact assessment, etc. of the enterprise must comply with the relevant procedures in accordance with the law. If the construction project fails to pass the energy-saving assessment review or environmental impact assessment approval, construction shall not be allowed to start; projects under construction that have not passed the energy-saving assessment review or environmental impact assessment approval, or projects that have failed the completed energy-saving assessment review or environmental protection acceptance, and projects that do not meet the safety production conditions, should stop construction and production; viscose fiber enterprises that have not obtained the pollutant discharge permit in accordance with the regulations should immediately stop production in accordance with the law, and can only resume production after obtaining the pollutant discharge permit. | Delete this item |
Overall, the 2024 edition of the document puts forward more stringent and detailed requirements than the 2017 edition in many aspects, especially in terms of resource consumption, carbon emissions and quality management, reflecting the trend of continuous updating and improvement of industry regulatory conditions over time.
2017 edition | New, deleted or adjusted content in the 2024 edition | |
Introduction | Emphasis on preventing low-level duplication and reducing resource waste | Emphasis on promoting green transformation and reasonably guiding the direction of industry development |
Enterprise layout | Emphasis on new construction in non-specific areas | Emphasis on concentrated construction of new projects in industrial parks |
The construction of new VFY projects are prohibited. Strictly control the construction of new VSF projects. New projects must have the conditions of replacing traditional raw materials such as cotton linter pulp and wood pulp through independent development, and realizing pulp and fiber integration, or having raw material bases that match the new capacity. | Delete this item | |
Advantageous enterprises mergers and reorganizations to enhance industrial concentration and overall competitiveness | Delete this item | |
Allow viscose fiber enterprises and scientific research institutions to build a production line for small or medium-scale trials with no more than 5kt/yr capacity and a differentiation rate of more than 90%. | Change the content of the test line to "hundred-ton small test line, thousand-ton pilot line and differential fiber line of no more than 30kt/yr capacity (differentiation rate> 90%)" - and move this content to the process equipment column. | |
Process equipment | Add the content of "new viscose fiber projects should have a stable source of pulp, and encourage enterprises to develop and apply new pulp (bamboo pulp, hemp pulp, mushroom grass pulp, recycled pulp, etc.)" | |
Delete the content of "the product differentiation rate of the total capacity of the expansion and reconstruction of viscose fiber projects is higher than 30%" | ||
Adopt efficient continuous impregnation, pressing and crushing combined machine to ensure the qualified composition and crushing degree of alkali cellulose; adopt advanced aging machine to ensure the stability of temperature and time of alkali cellulose aging; adopt automatic batching and feeding system, and the yellowing process is automatically controlled by program. The yellowing machine should have safety devices such as pressure relief facilities (pressure relief valve or pressure relief membrane); adopt high pressure difference viscose dissolution process and crushing and grinding equipment to improve the dissolution and filtration performance of viscose; adopt continuous automatic filtering device and waste viscose processing device, and add advanced plate and frame filtering device when necessary to ensure the spinnability of viscose; VSF spinning equipment is selected according to the requirements of different varieties. In principle, equipment with good airtightness and variable frequency speed regulation is used; the acid bath circulation system of the acid station should adopt acid bath degassing device and waste acid liquid recovery and treatment device; the recovery system should adopt multi-stage flash evaporation and sodium sulfate preparation device, and the amount of sodium sulfate prepared should be more than 60% greater than the amount produced; for strict process control of production, the DCS distributed automatic control system should be adopted throughout the line; it is required to make comprehensive and efficient use of resources such as condensed water, cooling water, waste water, and waste heat. | In the VSF spinning section, spinning machines, drawing machines and cutting machines must have good sealing properties to effectively reduce the unorganized emission of sulfur-containing waste gas; the VSF line recovery system must be equipped with sodium sulfate recovery equipment such as multi-stage flash evaporation or one-step nitrate extraction, and the sodium sulfate recovery rate must reach more than 60% of the production volume or more than 500 kg of sodium sulfate per ton of product; new construction, renovation and expansion of VFY and VSF projects should be well equipped with waste gas collection, supporting combustion, catalytic oxidation, biological treatment, biological adsorption and other devices to effectively treat volatile organic compounds, low-concentration sulfur-containing waste gas and other atmospheric pollutants; the wastewater treatment unit of the viscose fiber factory should be designed with reasonable closed collection measures and treatment facilities to collect and treat sulfur-containing waste gas; to promote technological progress and product development in the industry, viscose fiber enterprises and scientific research institutions are encouraged to use 100-ton small test lines, 1,000-ton pilot lines and differential lines of no more than 30kt/yr capacity (differentiation rate > 90%) for technical research and product development, etc. | |
Resource consumption | The water intake per ton of VFY≤235 tons; the water intake per ton of VSF≤55 tons; the reuse rate of production water≥90% | The water intake per ton of VFY≤230 tons; the water intake per ton of VSF≤50 tons; the reuse rate of production water≥92% |
The comprehensive energy consumption per ton of VFY≤4,000kg of standard coal. The comprehensive energy consumption per ton of VSF≤1,000kg of standard coal | The comprehensive energy consumption per ton of VFY≤3,200kg of standard coal. Comprehensive energy consumption per ton of VSF≤900kg of standard coal | |
Environmental protection | Hazardous waste must be handled by qualified units. | Hazardous waste and other solid wastes are effectively utilized and properly disposed of, and the standardized environmental management assessment of hazardous wastes should be up to standard. |
Newly built and expanded viscose fiber coal-consuming projects in key areas of Beijing-Tianjin-Hebei, Yangtze River Delta and Pearl River Delta should implement equal or reduced coal substitution. | Delete this item | |
Newly built and expanded VSF units should adopt advanced and reliable CS2 recovery units, and the total sulfur recovery should be more than 87%. | Delete this item | |
Carbon emissions | Viscose fiber enterprises are encouraged to carry out basic research and capacity building related to green factory construction, factory carbon verification, product carbon footprint, carbon labeling and product life cycle evaluation; viscose fiber enterprises are encouraged to formulate carbon reduction plans, carbon peak and carbon neutrality goals and disclose work progress regularly; viscose fiber enterprises are encouraged to equip solar street lights, photovoltaic panels and other carbon reduction projects according to the factory conditions, build and apply industrial green microgrids; viscose fiber enterprises are encouraged to adopt engineering facilities such as centralized heating, coal to gas, and coal to electricity to reduce corporate carbon emissions. | |
Quality management | Add the content of "intelligent manufacturing, digital workshop and smart factory construction. Improve the level of digital networking and intelligence, strengthen enterprise management, reduce production costs, and ensure product quality". | |
Safe production | Add the content of "the enterprise has not had a major or above production safety accident within one year". | |
Supervision and management | New (renovation and expansion) viscose fiber projects should comply with national laws and regulations and the requirements of this specification. The investment management, land supply, energy-saving assessment review, and environmental impact assessment, etc. of the enterprise must comply with the relevant procedures in accordance with the law. If the construction project fails to pass the energy-saving assessment review or environmental impact assessment approval, construction shall not be allowed to start; projects under construction that have not passed the energy-saving assessment review or environmental impact assessment approval, or projects that have failed the completed energy-saving assessment review or environmental protection acceptance, and projects that do not meet the safety production conditions, should stop construction and production; viscose fiber enterprises that have not obtained the pollutant discharge permit in accordance with the regulations should immediately stop production in accordance with the law, and can only resume production after obtaining the pollutant discharge permit. | Delete this item |
- Top keywords
- Cotton Price
- Cotton Futures Price
- Cotton Futures
- CZCE
- PTA Futures Price
- Chemical Fiber
- Polyester Prices
- Wool price
- PTA Futures
- Shengze Silk
- China
- Yarn Price
- price
- China Textile City
- Fibre Price
- Benzene Price
- Cotton
- Index
- Cotton Index
- PTA
- fabric price
- NYMEX
- Top 10
- textile industry
- Spot Cotton
- Cotton Yarn
- Polyester Price
- Futures
- PTA Price
- cotton yarn price